High Court overturns permission for Cork wind farm, Irish Times, 25 February 2016

Judge says process used by An Bord Pleanála did not comply with Irish law

The High Court has overturned a grant of planning permission for a wind farm near Inchigeelagh, Co Cork.
Mr Justice Bernard Barton ruled the permission must be quashed after finding that the process under which An Bord Plean├íla had decided relevant issues concerning compliance with two European Directives – the Habitats Directive and the Environmental Impact Assessment Directive – did not comply with Irish law.

Click here to read the full article